Way forward
- Test demands for **July 2017 to December 2018** against the ruling
- Challenge **section 74** where invoked for this period
- Keep evidence that panels are **detachable**
- 70:30 still applies **from 1 January 2019**
Under Serial No. 234 of Schedule I to Notification No. 1/2017-Central Tax (Rate) dated 28 June 2017, renewable energy devices and parts for their manufacture, including a ‘solar power generating system’, carry central tax of 2.5%, with the same again as State tax. From 1 January 2019, Notification No. 24/2018-Central Tax (Rate) dated 31 December 2018 added an Explanation to that entry: where such goods are supplied with a taxable service under Serial No. 38 of Notification No. 11/2017-Central Tax (Rate), 70% of the gross consideration is deemed the value of the goods and 30% the value of the service. Circular No. 163/19/2021-GST dated 6 October 2021 then said that tax on such projects can be paid on the 70:30 basis for 1 July 2017 to 31 December 2018 as well.
The CGST authorities read that Circular as a mandate. On 16 November 2026 the Supreme Court (Justice Sanjay Kumar and Justice Sanjeev Sachdeva) held that it is not, in Sterling and Wilson (P.) Ltd. v. Union of India [2026] 192 taxmann.com 377 (SC), Civil Appeal No. 14228 of 2026. The following covers the facts, what the Court held on each point, and what they mean for solar contractors with demands for the period before 2019.
The facts and the demand
The appellant supplies and installs solar power generating systems on a turnkey basis under EPC contracts, in several States. For supplies between 1 July 2017 and 31 December 2018 it paid 5% on the whole value under Serial No. 234 (para 6).
A show cause-cum-demand notice dated 29 March 2023 proposed tax on the 70:30 basis, at 5% and 18%. The Joint Commissioner, Thane, by order dated 17 January 2025, treated the contract as a works contract under section 2(119) of the Central Goods and Services Tax Act, 2017 (CGST Act), held the solar plant to be immovable property, and found wilful misstatement and suppression. That brought in the extended period under section 74 and penalty under section 122(2)(b) (para 18). CGST of ₹13,33,95,241 was demanded with equal penalty, plus the same under the State Act: ₹53,35,80,964 in all (para 2).
The Bombay High Court dismissed the writ petition on 28 July 2025 because an appeal was available, leaving the appellant to make the pre-deposit (paras 2 and 3).
Writ jurisdiction: an alternate remedy is not a bar in every case
The Supreme Court held that cursory dismissal was not justified, since the petition raised arguable points that the High Court should have considered (para 5):
Availability of an alternate remedy barring the invocation of a High Court’s writ jurisdiction is not a straitjacketed formula to be applied without exception.
The Court would ordinarily have sent the matter back. Because it had been argued at length, and the Andhra Pradesh High Court had already decided the same issue, it decided the merits itself. For taxpayers facing a large pre-deposit on a point of law already settled elsewhere, this paragraph is worth citing.
The 70:30 split is prospective, and the Circular gave an option
The 70:30 Explanation came in on the GST Council’s recommendation at its 31st meeting on 22 December 2018, to end disputes over how EPC contracts for solar systems should be split. Clause 2 of Notification No. 24/2018 brought it into force on 1 January 2019, and Notification No. 27/2018-Central Tax (Rate) dated 31 December 2018, which inserted Serial No. 38 in Notification No. 11/2017, took effect the same day (paras 11 and 13). The Court’s illustration shows what was at stake: on ₹10,000, tax was ₹500 before that date and ₹890 after, an effective 8.9% (para 12).
At its 45th meeting on 17 September 2021 the Council itself recorded that the 70:30 method was prospective. Taxpayers had asked to use the ratio for earlier supplies as well, and the Circular, issued under section 168, accepted that request: tax ‘can’ be paid at 70:30 for 1 July 2017 to 31 December 2018, with no refund where the tax already paid was more (paras 14 to 17).
The Court read ‘can’ as a choice left to the taxpayer (paras 17 and 33). In its words:
Thus, it is pristinely clear that only an option was given to assessees who wanted to take recourse to the new scheme, that came into effect from 01.01.2019, even for the period prior thereto if they so chose.
Neither the notification nor the Circular required the ratio to be applied to past supplies regardless of the taxpayer’s choice. Treating the option as binding on everyone was held ‘patently erroneous and wholly unsustainable’ (para 33).
One detail in the text: para 33 refers to the period ‘01.01.2017 to 31.12.2018’, while the Circular, as summarised at para 15, covers 1 July 2017 to 31 December 2018. The dispute, and the period stated in the Circular, both begin on 1 July 2017, so para 33’s date reads as a slip.
No section 74 for a regime that did not exist
Since the 70:30 regime began only on 1 January 2019, the Court held that fraud, wilful misstatement or suppression could not be imputed for not applying it to earlier supplies, and the extended limitation was ‘completely unsustainable on facts and in law’ (para 34). It followed Tata Steel Limited v. Union of India [2026] 189 taxmann.com 520 (SC): the facts behind an allegation of fraud or suppression must appear from the notice itself, and using those words is not enough.
Where a notice for this period alleges suppression only because the 70:30 ratio was not adopted, the demand fails on limitation as well as on merits.
Solar systems are not a works contract
Every works contract is a composite supply, but not every composite supply is a works contract. Under section 2(119), it must relate to immovable property as the end product (para 36). Applying the six tests in Bharti Airtel Limited v. CCE (2024) 19 SCC 1 (nature and object of annexation, intention of the parties, functionality, permanency and marketability), the Court held that solar panels fixed to a civil foundation, which keeps them stable and can be detached for use elsewhere, are not immovable property. Civil work in the EPC contract does not by itself make it a works contract (para 35).
The Court approved the Andhra Pradesh High Court’s consistent view: the appellant’s own case, Sterling and Wilson (P.) Ltd. v. Joint Commissioner [2025] 170 taxmann.com 539 (Andhra Pradesh), decided on 10 January 2025, which the Revenue did not challenge, and the later rulings on wind turbine generators and solar pumping systems. The Revenue’s challenge in the wind turbine case, Siemens Gamesa Renewable Power, had already been dismissed by the Supreme Court, 2026 (8) TMI 847 (SC) (paras 28 to 31 and 36).
The Court noted the undisputed fact that the panels could be detached (para 35). Contractors should keep the drawings, mounting details and contract terms that show this.
The 2021 change of entry
Notification No. 8/2021-Central Tax (Rate) dated 30 September 2021 omitted Serial No. 234 from Schedule I and inserted Serial No. 201A in Schedule II, which names a ‘solar power generator’ without the word ‘system’. The Court read this as a sign that, earlier, the whole system was taxed as one unit, and held that the substitution cannot apply to supplies made before it (paras 37 and 38).
What follows
The appeal was allowed and both the order of 17 January 2025 and the Summary Order of 24 January 2025 were set aside (para 40).
Demands for 1 July 2017 to 31 December 2018 that rest on the 70:30 ratio, on works contract classification of a detachable solar system or on section 74 can now be met with a direct Supreme Court ruling. The ruling does not disturb the 70:30 basis from 1 January 2019, which applies by notification. Contractors that chose to pay at 70:30 for the earlier period under the Circular should note its condition that no refund is given where the tax already paid was more.
This article is intended for educational purposes only and should not be construed as professional advice. It is based on the law as understood on the date of publication; laws and regulations are subject to change, and it may not reflect later developments. Readers are advised to consult a qualified tax professional on their specific situation before taking any action based on it. CA. Mohit Gaba takes no responsibility for any action taken or decision made on the basis of this article.
Common questions
Can GST officers apply the 70:30 split to solar power systems supplied before 1 January 2019?
No. In Sterling and Wilson (P.) Ltd. v. Union of India [2026] 192 taxmann.com 377 (SC), decided on 16 November 2026, the Supreme Court held that the 70:30 deemed valuation inserted by Notification No. 24/2018-Central Tax (Rate) operates only from 1 January 2019. Supplies from 1 July 2017 to 31 December 2018 that paid 5% on the whole value under Serial No. 234 of Notification No. 1/2017-Central Tax (Rate) cannot be re-taxed on the 70:30 basis.
Does Circular No. 163/19/2021-GST make the 70:30 ratio compulsory for 2017-18?
No. The Supreme Court read the Circular's words that tax 'can' be paid at 70:30 for 1 July 2017 to 31 December 2018 as an option for taxpayers who wished to adopt it. Neither the Circular nor the notification required the ratio to be applied to taxpayers who did not choose it.
Is supply and installation of a solar power plant a works contract under GST?
Not where the solar panels can be detached from the civil foundation and used elsewhere. The Supreme Court held that a composite supply is a works contract under section 2(119) of the CGST Act only if immovable property is the end product, and that fixing a solar power generating system on a foundation for stability does not make it immovable property, even if the contract includes some civil work.
Can section 74 be invoked for solar EPC supplies made before 1 January 2019?
No, on the Supreme Court's view in Sterling and Wilson. Since the 70:30 regime did not exist before 1 January 2019, fraud, wilful misstatement or suppression could not be imputed for not applying it to earlier supplies, and the extended limitation was held unsustainable.